Novation Agreement
Novation is the transfer of
contractual rights and responsibilities from one party to another. While the
benefits of a contract can be transmitted by assignment, the parties must use a
novation agreement to transfer both the benefits and the liabilities.
A novation happens when one
contract is canceled and replaced with a new contract in which the original
contractual duties are carried out by different parties. In the context of
building design and construction, novation typically refers to the process
through which design consultants are first engaged to the employer but later 'novated' to the contractor.
This is common on design and
build projects where the design team is appointed by an employer to conduct
preliminary studies or prepare a concept or detailed design, but when a
contractor is appointed to carry out or complete the design and construct the
works, the design team (or a part of the design team) is novated to work for
them.
This can be advantageous to employer
s because it preserves continuity between pre-tender and post-tender design
while leaving the contractor solely responsible for designing and building the
project.
The procedure of novation does
not hold a contractor liable for any design work done for the employer prior to
novating their contract. To accomplish this, the building contract must clearly
declare that the contractor studied and adopted the design.
Documentation of the Novation Agreement
Without approval, a novation
agreement is not feasible. If novation and the terms of the novation agreement
were not agreed upon when the consultant was first hired, they are under no
duty to consent to be novated. It is also critical that the primary contracts
between the employer and the consultants, as well as the primary contracts
between the employer and the contractors, have specific language requiring the
contractor and the consultant to enter into the novation agreement.
To eliminate the risk of simply
agreeing to an unenforceable agreement, a specimen form of the proposed
novation agreement should be affixed to the original contractual instrument.
It is critical that any
novation documentation is properly drawn up and makes clear which services
consultants performed for the employer and which they will now perform for the
contractor; otherwise, initial appointment agreements, such as a requirement
for the consultant to inspect the contractor's work and report to the employer,
may be rendered meaningless when they are in fact now appointed by the
contractor.
Kinds of Novation
Standard: When two
parties agree that additional conditions must be added to their contract,
creating a new one.
Expromissio: This
novation must involve three parties: a transferor, a counterparty, and a
transferee. All three parties must agree to the new terms and enter into a new
contract.
Delegation: One of the
contract's parties transfers their responsibilities to a new party, legally
tying that party to the contract's provisions.
Novation vs. Assignment
An assignment transfers rights
or property from one person or business to another. However, the assignment
merely transfers the benefits; any duties stay with the original contract
party. The new party receives benefits and potential liabilities due to the
novation.
Another significant difference
is that novation requires the approval of all parties involved, which is why
novation is nearly often accomplished through a tripartite agreement. Subject
to the precise provisions of the contract, it is not necessarily essential to
get consent in the case of an assignment.
Novation Subcontractor of Construction Contract
A novation agreement transfers
a construction subcontractor's rights and duties from the first (in
administration) contractor to a second (solvent) contractor.
Changing a consultant's
appointment from the professional consultant and the employer to the
professional consultant and the contractor under a novation agreement. A deed
of novation is typically used on a construction project to transfer the
appointment of a professional consultant from the employer and the professional
consultant to the design and build contractor and the experienced consultant.
Novation Agreement Consideration
Most common Design-Build contracts allow for novation and include standard novation deeds. The following
issues should be taken into account and handled by parties to a novation deed:
Release
The standard novation deed
includes a general release in which the outgoing and continuing parties release
each other from all claims arising from the original contract. Parties should obtain clarification on the
novation's impact on accrued rights, claims, and demands arising from the
original contract, as well as all future rights, claims, and demands.
Warranty
The requirements of the
standard deed of novation include a warranty by both the outgoing and
continuing parties that the work completed by the continuing party under the
original contract is in conformity with the provisions of the original
contract.
Risk management
The crucial point is that the insurance program
for the consultant must be properly structured to meet this potential gap.
Advantages and Disadvantages of Novation in Construction
Advantages of Novation are:
A Reduced
Learning Curve:
Working with the customer early on allows the architect to obtain a thorough
understanding of the customer's needs. If the architect is not novated, this
knowledge may be lost, and parts of the process may have to be repeated with a
new design team. This can be damaging to the ultimate design of a complex or
highly technical undertaking. Novation can give some economies of scale that
the customer can benefit from in terms of the design team's learning curve. If
the architect knows they will be involved throughout the process, not just
during the pre-contract and tender stages, there is a chance of achieving a
lower overall cost. Not to mention the time and money it takes to brief a new
design team.
Reduced
Contractual Risk for the Employer: The procedure of novation and the
transfer of responsibility to the contractor implies that the employer
contractually accepts minimal risk while yet having control over project
design. Of course, exact contracts vary, but at the point of novation, the Design-Build contractor is responsible for all future design work, which can
occasionally extend to cover all previous design work accomplished prior to the
contract being granted (including any design errors). As the contract proceeds,
the employer only has to deal with one company: the contractor. This streamlined
method benefits the employer by removing the possible complications and hassles
of interacting with many organizations to resolve issues.
Early design
development improves cost certainty: Cost certainty is better in Design-Build projects when the initial employer's needs are most precise. Novation
assists customers in achieving a well-developed design early in the process by
providing the architect with clarity across the duration of their
collaboration. If the architect is satisfied that the scheme will move forward
and is not working "at risk," they are more inclined to develop the
design further, providing for a more accurate grasp of costs during the tender
stage and boosting total cost certainty.
The Contractor
has more influence and control over the design: Traditional contracts
have the potential for conflict between the contractor and the design team over
who is responsible for flaws and whether they are the consequence of a design
or construction quality issue. This often puts the employer in a tough position
and raises the likelihood of the parties reaching a 'stalemate. 'Novation helps
to avoid this problem; in an integrated design and construction team, the
contractor is automatically responsible for resolving the issue. These concerns
should potentially appear less frequently in a novated Design- Build contract
because the designer and contractor worked closely to jointly develop and agree
on the final design, as well as to ensure buildability and quality. Through the
influence of design decisions at each level, the contractor is better
positioned to manage and control the risk to quality.
Whereas The Disadvantages of
Novation are:
The Contractor
and Architect Must Have a Good Relationship: On every Design- Build project,
the contractor and architect must collaborate closely, but this is more crucial
when novation has occurred. Novation is frequently criticized for putting
further strain on these parties' relationship. Without a healthy relationship,
there is a larger possibility that the project will suffer and crucial concerns
such as time and cost will suffer.